An appeal of the Planning Commission's 4-3 conditional approval of a new public works operations center — CUP, Class 2 design review, and water resource permit — on about 5.7 developed acres of a 33-acre Salamo Road site.
Impact summary
If approved as staff recommends, the facility replaces the aging existing yard but neighbors want stronger evidence on slope stability, traffic and noise before any approval.
Applicant
- Name
- City of West Linn Public Works Department
- Address
- Salamo Road, West Linn, OR
At a glance
- Hearings
- 3
- Public comments
- 0
- Total mentions
- 3
Last vote · Planning Commission
Last discussed May 27, 2026.
Meeting timeline (3)
Hearings Officer Appeal of the Planning Commission’s approval of the City of West Linn Operations Center - May 27, 2026
An appeal of the Planning Commission's 4-3 conditional approval of a new public works operations center — CUP, Class 2 design review, and water resource permit — on about 5.7 developed acres of a 33-acre Salamo Road site.
Planning Commission Meeting - Feb 18, 2026
A combined conditional use permit, Class 2 design review, and water resource area permit for a new public works operations complex on two vacant, heavily wooded lots 50-60 feet below Salamo Road. No decision was made; the hearing was continued to March 4 with the record open until Feb. 25.
Planning Commission Meeting - Feb 4, 2026
A five-building, 40,000 sq ft complex serving public works, environmental services, parks and rec, and water/streets on 33 wooded acres, with permanent impacts to 15,120 sq ft of wetland buffer and stream area. Staff recommended approval with conditions; the hearing was continued to Feb 18 after extensive neighbor testimony about landslide risk, traffic and noise.
Related issues (4)
Drinking water system funding and the 5% utility rate cap
The city faces major drinking water capital needs at both South Fork Water Board and the city system, with rate caps limiting revenue. Council expects big conversations about water rates after the new year.
Public hearing procedure compliance (CDC 99.170)
A remote speaker said the city failed to mail her notices of the Planning Commission decision and this hearing, published the agenda only six days ahead, and couldn't accommodate her wheelchair access to review the record.
Consolidation of city operations into one new facility
The Council was scheduled to discuss a contract amendment for early work on the Operations Complex, the city's facilities project. The terms of the amendment and its cost implications were not recorded.
Single point of access and emergency response
Several commissioners pushed hard for a second way out of the facility — potentially across ODOT property to I-205 — arguing one road through landslide terrain is not enough for an emergency operations center. Because no code criterion supports mandating it, the commission could only attach an advisory condition encouraging the applicant to study the idea.
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for West Linn, OR
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.