Critical PriorityDevelopmentopen

Tandler Drive appeal delegation to hearings officer

Summary

The project requires rerouting Tannler Drive through the site to align with a signalized intersection at Blankenship Road, at an estimated cost of about $4-5 million. Neighbors fear losing the street they've used for 25 years, longer routes to I-205 and reduced park access; the applicant says the existing failing intersection leaves no alternative.

At a glance

Total mentions
12
Last 30 days
1

Discussed at 2 meetings in the last 60 days; most recently Oct 28, 2026.

Impact analysis

💰Financial impact

The applicant estimates roughly $4.9 million in road improvements and is proposing to pay 29% of the cost; city staff floated around 20% for the city.

✅Who benefits

New residents and the surrounding area get a signalized, safer intersection — but only if the road is moved.

⚠️Who could be affected

Neighbors along the existing Tannler Drive alignment lose familiar direct access and worry about traffic on nearby streets.

Mentions & discussions (5)

MeetingOct 28, 2026

Hearings Officer Appeal - Class 2 Design Review and Lot Line Adjustment on Tannler Drive - Oct 28, 2026

The project requires rerouting Tannler Drive through the site to align with a signalized intersection at Blankenship Road, at an estimated cost of about $4-5 million. Neighbors fear losing the street they've used for 25 years, longer routes to I-205 and reduced park access; the applicant says the existing failing intersection leaves no alternative.

MeetingSep 22, 2026approved

City Council (Special) - Sep 22, 2026

The ~320-unit apartment project near Blankenship was recommended for denial by the Planning Commission, and the applicant has appealed — plus filed a complaint with the state's housing accountability office. The council decided 4-1 that an outside hearings officer, not the elected council, will decide the appeal, citing new state housing laws and political pressure.

MeetingAug 26, 2026denied

Planning Commission Meeting - Aug 26, 2026

A 320-unit apartment and commercial project at Tannler/Blankenship was denied 5-0 over code compliance failures. Neighbors' concerns about parking, traffic, and egress played into the deliberation.

MeetingAug 10, 2026

Planning Commission Meeting - Aug 10, 2026

A 320-apartment, roughly 11,600-square-foot commercial project is proposed on 11 acres of steep, office-business-zoned land near I-205. Neighbors worry about traffic on the only two routes up the hill, parking overflow, stormwater vaults on landslide-prone slopes, removal of about 80% of on-site trees, and loss of park access if Tannler Drive is realigned.

OregonLive.comMay 28, 2026

Appeal heard over West Linn plan to build on landslide site

Appeal heard over West Linn plan to build on landslide site OregonLive.com

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for West Linn, OR

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.